Project Updates – December 2015

calendar Icon
January 4, 2016

Major Activities

Structure

Four additional concrete elevator core pours were completed in November and the core continues to rise above 5th Avenue. At the end of November, the elevator core reached Level 8. In December the core cycle will be reduced by one day. The tower crane was jumped 100’ in late November to allow for core construction to continue. The next tower crane jump is scheduled for late January. Structural steel pre-work is ongoing in preparation for primary garage steel erection commencement in early January.

Public Impacts

5th Avenue

For safety, the west sidewalk between Columbia Street and Marion Street will remain closed to pedestrians throughout the duration of the project. The west side traffic lane will be closed for construction Monday – Friday, between 6 p.m. and 3 p.m. and on Saturdays (9 a.m. to 6 p.m.) as required.

Columbia St

The north sidewalk between 5th Avenue and 4th Avenue will remain closed throughout the duration of the project as this is a concrete pumping station and will serve as the location for a construction elevator and other primary building functions.

Mobilizations/Street Closures

The next major road closure is approaching in February 2016, when the large steel columns that span from Level 1 to Level 5 will be erected. This will require a full closure of 5th Ave between Columbia and Marion Streets for 2 successive weekends. Periodic lane closures on Columbia St. will still be necessary for the next 2-3 months as the perimeter walls and steel erection for the parking garage on the west side of the project are completed.