Construction Milestones

Spring 2018

  • Opening of the Hotel

May 2017

  • Completion of the building and tenant move-in

October 2016

  • Completion of the garage

January 2016

  • Rehabilitation of the Sanctuary building commences

August 2015

  • Start constructing steel office tower structure and building systems

June 2015

  • Start constructing building foundations and parking garage structure

May 2015

  • Complete excavation and erect tower crane

November 2014

  • Issuance of revised Master User Permit by the City of Seattle

July 2014

  • Shoring and excavation commence